Cost guide, updated November 2026

How much does it cost to build a data center?

A new data center in the US or Canada costs about $8.9 million to $23.3 million per MW before GPUs, according to Cushman & Wakefield’s 2026 guide. The average for modern facilities is about $17.6 million per MW, so a 10 MW build comes to roughly $176 million.

Figures are third party estimates for early planning, not a quote.

By size

Data center cost by capacity

Multiply your planned megawatts by the per MW range to get a first budget range.

Estimated data center cost by capacity
CapacityLowAt averageHigh
1 MW$8.9M$17.6M$23.3M
10 MW$89M$176M$233M
20 MW$178M$352M$466M
50 MW$445M$880M$1.17B
100 MW$890M$1.76B$2.33B

Our arithmetic using the 2026 range of $8.9M to $23.3M per MW and the $17.6M average, before GPUs. Small projects can fall outside the range, and costs don't always scale evenly.

Budget breakdown

Data center construction cost by category

Power, the building and contingency make up more than half of a typical budget once GPUs are set aside.

Data center budget by category
CategorySharePer MW20 MW example
Power infrastructure21%$3.7M$73.9M
Core, shell and sitework17%$3.0M$59.8M
Contingency16%$2.8M$56.3M
Cooling12%$2.1M$42.2M
Owner furnished equipment8%$1.4M$28.2M
Site acquisition7%$1.2M$24.6M
IT and network, excluding GPUs7%$1.2M$24.6M
Design3%$0.5M$10.6M
Escalation3%$0.5M$10.6M
Not itemized6%$1.1M$21.1M
Total before GPUs100%$17.6M$352.0M

Shares are Cushman & Wakefield 2026 figures as compiled by GR1D and CRE Daily. Dollar amounts are arithmetic on the $17.6M average, not published line items.

Cost drivers

What moves the number

Market

Silicon Valley, Chicago, New York, Northern New Jersey, Toronto and Los Angeles are reported among the most expensive markets. Texas markets are reported among the least expensive.

Density and cooling

JLL estimates liquid cooling adds about $1M to $2M per MW compared with air cooled designs, and AI ready designs add 15% to 25% to shell and core cost.

Equipment prices

Reported increases from December 2021 to early 2026 include 60% for switchgear, 46% for copper, 33% for generators and motors, 32% for cooling equipment and 29% for transformers.

Lead times

Reported lead times run 68 to 113 weeks for pad mounted transformers, 60 to 100 weeks for generators and 38 to 63 weeks for medium voltage switchgear.

Comparing reports

Why cost per MW figures disagree

Published numbers measure different things. Check the scope before you use one in a budget.

Published cost benchmarks and what they cover
BenchmarkFigureSource and scope
New build average$17.6M per MWCushman & Wakefield, modern greenfield facilities in the US and Canada, before GPUs
New build range$8.9M to $23.3M per MWCushman & Wakefield via CRE Daily, US and Canada, before GPUs
Global average forecast$11.3M per MWJLL forecast for 2026, as reported by Datacentres.com. GR1D describes this as shell and core scope
GPUs, servers and network$29M to $42M per MWGR1D estimate derived from order and rack pricing
1 GW AI campusAbout $30BBloomberg analysis with Cushman & Wakefield, Abilene, Texas, including about $17B of chips

FAQ

Data center cost questions

How much does it cost to build a data center?

A new data center in the US or Canada costs about $8.9 million to $23.3 million per MW before GPUs, with an average of about $17.6 million per MW for modern facilities, according to Cushman & Wakefield's 2026 guide.

How much does a 10 MW data center cost?

Using the 2026 per MW range, a 10 MW data center works out to about $89 million to $233 million before GPUs. At the $17.6 million average, that is about $176 million. Use this as a rough planning figure, not a quote.

What is the biggest data center construction cost?

Excluding GPUs, power infrastructure is the largest category at about 21% of a greenfield budget. Core, shell and sitework is about 17%, contingency about 16% and cooling about 12%.

How much do GPUs add to the cost?

GR1D estimates that GPUs, servers and networking add about $29 million to $42 million per MW for high end AI systems. A Bloomberg analysis prepared with Cushman & Wakefield put a 1 GW AI campus at about $30 billion, with about $17 billion going to chips.

How much of the budget goes to land?

Site acquisition is about 7% of a greenfield budget in Cushman & Wakefield's category shares. GR1D also reports a powered land benchmark of about $584,000 per MW in primary US markets. These figures cover different scopes and do not reconcile exactly.

Why do cost per MW figures differ so much?

Reports measure different scopes. JLL forecasts a global average of $11.3 million per MW for 2026, while Cushman & Wakefield reports $17.6 million for modern greenfield facilities in the US and Canada. Always check what a figure includes before you compare it.

Are data center construction costs still rising?

Cushman & Wakefield reports a 21% average increase per MW since its late 2024 guide. Between December 2021 and early 2026, reported price increases include 60% for switchgear, 46% for copper and 33% for generators and motors.

How long do major electrical components take to arrive?

Reported lead times run 68 to 113 weeks for pad mounted transformers, 60 to 100 weeks for generators and 38 to 63 weeks for medium voltage switchgear. These lead times can shape your schedule as much as your budget.